|
TRAINING
THE
DES MOINES METROPOLITAN WRA
WASTEWATER RECLAMATION FACILITY
Construction
began in 1985, and was completed in 1993,
at a cost of nearly $250 million. These
facilities replace the former plant built
as a WPA project at this same site. The
new plant is designed to treat up to 190
million gallons of wastewater a day. The
plant is approximately one mile in length
and one-quarter mile in width at its widest
point. Approximately 120 professional people
operate and maintain the facilities twenty-four
hours a day, monitor effluent quality, and
manage a budget of $14 million staff it.
The
operation of the plant is paid through both
domestic and industrial user fees. (Our
current 1991 cost of treatment is $1.03/1000
gallons. This is minus administrative and
bond reduction cost.) Construction was financed
through the cooperative efforts of Federal,
State and local governments. The WRA consists
of Des Moines, Ankeny, Johnston, Bondurant,
Altoona, Urbandale, Clive, Windsor Heights,
West Des Moines, Pleasant Hill, Polk and
Warren Counties. The average American uses
1,280 gallons of water per day. The treatment
plant can serve over 300 million people.
Typically wastewater is 99.9% water. The
entire treatment process is typically to
treat pollution that is less than one tenth
of one percent. Our goal, in treating this
wastewater, is the protection of public
health and the environment by meeting our
federal and State discharge permits.
The Des Moines Metropolitan WRA Wastewater
Reclamation Facility consists of preliminary
and primary treatment, roughing filters,
secondary treatment processes with nitrification,
disinfection and anaerobic digestion.
Lift
Stations
The
water provided by the Des Moines Waterworks
is used by residents, industries and businesses
and is discharged into the sewer system.
The treatment plant operates and maintains
26 sanitary lift stations located throughout
the collection system. These lift stations
pump the wastewater from a lower sewer to
a higher sewer so that the flow arrives
at the plant essentially by gravity. The
lift stations are monitored by a modern
sophisticated computer surveillance system.
Each station is automatically contacted
by radio and its operational status surveyed
by radio each minute. In the advent of a
failure, an alarm is sounded and recorded
at the main control room. A team of highly
trained and experienced professionals is
then dispatched to the troubled station.
Often repairs are made without any disruption
of service. In addition to the automatic
surveillance, each station is routinely
visited by a crew to insure proper and dependable
operation. The treatment plant regulates,
through the pretreatment program, all of
the major industrial effluents into the
sewers to assure that toxic and improper
wastewater, that could contaminate the river,
residual solids or that could interfere
with the biological treatment processes,
are not discharged into the public sewers.
Due
to infiltration and inflow into the collection
system during wet weather periods, our effluent
flow can reach in excess of 220 MGD. Treatment
of this storm water can exceed $150,000
per day. To alleviate these flows, our crews
operate and maintain five flow equalization
facilities in addition to the lift stations.
A flow equalization structure temporally
stores excess flow in the collection system
for later release. As an example, the SW
Equalization Basin at 59th and Winona is
designed to hold approximately 10 million
gallons of storm water. After a storm and
the high flows at the main plant have receded,
this temporally stored water is released
back into the collection system for treatment.
The WRF operates 25 storm water stations.
Many of these stations screen the storm
water for floating debris prior to discharge
directly to the river while others pump
water over the levee when the levee gate
wells are closed to prevent the river from
backing up the storm sewer and into the
city. In total, the WRF crews operate, maintain,
and monitor 56 lift stations and 285 gates.
In addition, WRF personnel operate the Des
Moines’ Airport glycol station. This station
treats the glycol used in de-icing operations.
The
Distributive
Control
System
The
distributive control system consists of
21 separate computers that controls and
monitors the facility, thereby providing
the precision necessary to maintain the
complex processes at the treatment plant.
The computer system is a multi-bus 286/386
micro processor system with three command
stations and a historical collection system
used to collect data and print reports.
Seventeen distributive control systems (DCS)
collect the data, the operator command stations
(OCS) provide the man-machine interface
from which the operator can monitor and
control the process. The ICS (Information
Control Station) provides for the collection
of historical data and the production of
reports. Computer strategies and automatic
interfacing between the computer and field
equipment allows the computer to automatically
respond to changing conditions without operator
input. However, the operator can override
the computer and control the process through
the keyboard by typing in the correct commands.
And should the system fail, the operator
can control the plant from the equipment
control panels.
Flow
Through
the Plant
Two
sewer lines enter the main pump house. From
the east is a 60" sewer line and from
the west is the 96" south-side interceptor.
The west sewer line flows through a diversionary
structure where the amount of flow coming
into the plant can be controlled. Excessive
flows can be bypassed to the Des Moines
River at this point. However, it is important
to note that the wastewater will be diluted
with large amounts of storm water. The flow
from the two sewer lines join and pass through
four bar screens. Bar screens are similar
to the bars you would imagine in a jail,
but closer together. As the sewage passes
through the bars, large items (i.e. rags,
sticks, paper, etc.) are caught. These bars
are mechanically cleaned and the debris
is carried up to the first floor. The screenings
can be diverted to either an augur or a
dumpster. Lime can be applied to the screenings
in the dumpster. This alkaline material
kills bacteria and controls odors. This
is called chemical stabilization. The augur
transports the screenings to a washer. The
screenings are then dried and can then be
bagged and placed into a dumpster. The screenings
are taken to the sanitary landfill for burial.
After
screening, the influent wastewater enters
a wet well. Here, six centrifugal pumps,
each driven by a 700 horsepower motor, lift
the sewage 54 feet into a channel and a
parshall flume where the flow will be measured.
Four of these pumps are variable speed,
two are constant speed. Each is capable
of pumping 38,192 gpm.
Next
is another physical treatment process, grit
removal. There are six aerated channels
that slow the flow to one foot per second.
Here, sand, gravel, and similar material
drop to the bottom. Later, the overhead
gantry crane will be used to remove the
grit. The grit is stabilized in building
12, the residuals handling facility.
Now
the flow divides and flows down the east
and west primary influent channels and through
the splitter boxes into the primary clarifiers.
This is another physical treatment process
in which floatables (grease and scum) and
fine solids are removed. Each primary is
130 feet in diameter and approximately 12
feet deep. Each holds 1.19 million gallons.
Generally, a retention time of 1 to 2 hours
is maintained, allowing the scum to float
to the surface where it is removed by a
skimmer. The floatables are pumped to building
12 for further processing. The solids, that
settle to the bottom, are removed by a bottom
scrapper and pumped to the blended sludge
wet well. Here, the primary sludge will
be mixed with the thickened waste activated
sludge and pumped to the anaerobic digesters.
The
liquid portion, containing dissolved and
suspended organics, overflow the weirs and
into the 108" line leading to the roughing
filter control chamber. This chamber will
allow up to 97 MGD to the roughing filters.
Any excess, up to 93 MGD will go directly
to the aeration basins. Any flow in excess
of 190 MGD will be bypassed directly to
the river.
There
are twelve roughing filters that are 152
feet in diameter and 7 feet deep. They are
filled with rock that are 2 to 5 inches
in diameter. On the surface of this rock
live millions of microorganisms. These organisms
use the dissolved, suspended and colloidal
organics in the wastewater as food. This
is an aerobic biological and secondary treatment
process. As the wastewater splashes on the
rock, oxygen is dissolved into the water.
The microorganisms use this dissolved oxygen
to live. As they grow and reproduce, the
organics are removed. When the bacteria
slough off the rock, they will eventually
be removed in the final clarifiers.
The
aeration basins are the structures for the
activated sludge process. Activated sludge
is also an aerobic biological and secondary
treatment process. The microorganisms live
on small particles of sludge instead of
rock. Because these particles are so much
smaller, billions more bacteria can be grown
in a smaller space. But they now use oxygen
at a much faster rate than can be dissolved
naturally into the water. To insure that
they have plenty of oxygen, four 2000 horsepower
motors blow filtered air through fine diffusers
in the bottom of the basins. There are six
aeration basins, each with four passes.
They are 300 feet long, 140 feet wide, and
20 feet deep. Each basin holds 6.48 million
gallons. In the latter passes, nitrification
occurs. That is, ammonia is converted to
nitrates.
After
the activated sludge process, the mixed
liquor flows to the final clarifiers. There
are twelve clarifiers, each 140 feet in
diameter, and 14 feet deep at the sides.
Each holds 1.66 million gallons. Here, the
activated sludge settles very rapidly to
the bottom and is removed. Most of the sludge
will be returned to the beginning of the
activated sludge system to be used again.
Some of it will be wasted to one of three
large centrifuges. Here some of the water
will be removed. The thickened wasted activated
sludge is mixed the primary sludge in the
blended sludge wet well and pumped to the
digesters.
The
liquid flows to the disinfection process
to kill most bacteria. The
final effluent discharged to the river is
now cleaner than the river itself with a
BOD5 less than 5 PPM, ammonia
less than 5 PPM, and suspended solids less
than 5 PPM. Also, not only as a cost saving
measure, but as an important conservation
measure, we reuse a portion of the final
effluent for process and washing water.
|